3.1i Foundation ISE: Translation Report and Fitter Report gain checkmark after reload

説明

Keywords: Fitter, Hitop, ISE, Project Navigator Checkmark, status

Urgency: Standard

General Description: Once the Fitter or Implement Design process
has been run and neither the Translation or Fitter report have been
viewed, when the project is re-opened the two reports will have a
green checkmark.

ソリューション

This is a visual indication that the report is preset and up to date.
AR# 9320
日付 01/16/2003
ステータス アーカイブ